The parking garage is scheduled for completion in late July!!
Thank you for your patience during the construction phase! See updates below.
Construction Timeline
- The construction fencing was placed November 4th
- Demo began on November 11th
- Foundation and first story walls - December - March
- First ramp in place! March 19th
- Crane has arrived and is placing pre-cast components for 5 levels. Will be about 60ft high - March-April
- Construction is moving from North to South along Jackson Street & Avendia de las Americas